Just go through the piece of information from one of the press releases of the Ministry of New and Renewable Energy and you can judge by yourself after looking at the last two columns of the table given at the end that how much was the target and how much could have been achieved.
This is self explanatory that how
much attention and care is needed to fulfill the dream of a green powered
nation.
The Ministry of New and Renewable
Energy is implementing a number of schemes / programmes, throughout the
country, for the development and tapping of renewable energy potential. A
capacity addition of 11,262 MW against a target of 10,522 MW has been achieved
from various renewable energy sources during the last three years. During
2013-14, a capacity addition of 640 MW has been achieved till 30.06.2013
against the target of 4325 MW.
Among the other steps to promote
power generation from renewable energy are, setting up of demonstration
projects, intensive resource assessment, development of power evacuation and
testing facilities.
Source wise targets and achievements of power generation during last three years and current year (Till 30-06-2013) :
S. No.
|
Programme / system
|
2010-11
|
2011-12
|
2012-13
|
2013-14
|
||||
Target
|
Ach.
|
Target
|
Ach.
|
Target
|
Ach.
|
Target
|
Ach.
(as on 30.6.13)
|
||
1.
|
Wind
Power
|
2000
|
2350.00
|
2400
|
3197.00
|
2500
|
1699.00
|
2500
|
512.00
|
2.
|
Small
Hydro
|
300
|
307.22
|
350
|
353.00
|
350
|
237.00
|
300
|
54.00
|
3.
|
Bio
Power
|
472
|
473.50
|
475
|
487.90
|
475
|
472.00
|
425
|
-
|
4.
|
Solar
Power
|
200
|
26.59
|
200
|
905.00
|
800
|
754.00
|
1100
|
74.80
|
Total
|
2972
|
3157.31
|
3425
|
4942.90
|
4125
|
3162
|
4325
|
640.00
|